Timelines are based on the current list of registrations from jointruestream.com, which changes daily, and the current number of crews working. These dates are for drop construction progress. The drop brings the fiber line from the mainline to the side of the home. The drop generally follows the path of your electric, overhead, or underground. 

Estimated times are for construction only. Installations in the home will follow AFTER construction has been completed, and we have confirmed the fiber line to your home is operational.

Now let’s get to the important stuff!

Construction is in full swing. Crews have completed over 520 drops and we have added 459 new Truestreamers so far this month!

To find out which area you are in, log-in to your account at jointruestream.com and view your dashboard.


Petoskey Service Area

For everyone who HAS returned their paperwork BEFORE May 1, 2020:

    • Mainline construction is COMPLETE!
    • Drop construction is COMPLETE!
    • In-home installations are still ongoing.

For everyone who registered and returned their paperwork AFTER May 1, 2020:

    • Design, drop construction, and in-home installations will continue, but you may experience a delay.

For everyone who HAS NOT returned their paperwork or registered their interest:

It’s not too late! Register by October 1st and return your paperwork by October 31st to guarantee FREE in-home installation. PLEASE NOTE: construction and installations in the area are ongoing, but you may experience a delay. Don’t miss out! Visit www.jointruestream.com to register today!

 

 

 

 


Boyne Phase 1

For everyone who HAS registered their interest and returned their paperwork BEFORE August 1, 2020:

  • Boyne City 3
    • Mainline construction is complete
    • Based on current registrations and crews, most drops in the Boyne City 3 area are projected to be COMPLETED by late fall.
    • After the drop construction is complete and we have verified the fiber line to your home is operational, we will call to schedule the in-home installation.
  • Boyne City 1 and 2
    • Mainline construction is complete
    • Based on current registrations and crews, most drops in the Boyne City 1 and 2 areas are projected to be COMPLETED by late fall.
    • After the drop construction is complete and we have verified the fiber line to your home is operational, we will call to schedule the in-home installation.
  • Advance and Deer Lake
    • Mainline construction is complete.
    • Based on current registrations and crews, most drops in the Advance and Deer Lake areas are projected to be COMPLETED by winter 2021.
    • After the drop construction is complete and we have verified the fiber line to your home is operational, we will call to schedule the in-home installation.

 

 

 

 


Boyne Phase 2

Boyne Phase 2 ma

  • East Jordan Areas
    • Mainline construction continues.
    • Based on current registrations and crews, drops in the East Jordan areas are projected to BEGIN in early 2021.
    • After construction is complete and we have verified the fiber network and line to your home are operations, we will call to schedule the in-home installation.
  • Central Lake and Eastport Areas
    • Mainline construction has begun in the Central Lake 2, 3 and 4 and Eastport 1, 2 and 3 areas.
    • Based on current registrations and crews, drops in the Central Lake and Eastport areas are projected to BEGIN in the spring 2021.
    • After the drop construction is complete and we have verified the fiber line to your home is operational, we will call to schedule the in-home installation.
  • Barnard and Milton Areas
    • Mainline construction will begin in the late fall.
    • Based on current registrations and crews, drops in the Barnard and Milton areas are projected to BEGIN in the summer 2021.
    • After the drop construction is complete and we have verified the fiber line to your home is operational, we will call to schedule the in-home installation.

 

 

 

 

 

 


Boyne Phase 3

Boyne Phase 3 Map

  • Elmira & Corwith
    • Mainline construction will begin in the spring of 2021
    • Based on current registrations and crews, we expect to begin the drop installations in the Boyne phase 3 areas in the summer of 2021 and will continue until they are complete.
    • After construction is complete and we have verified the fiber line to your home is operational, we will call to schedule the in-home installation.

 

 

 

 

 


Fielding Exploration

Hart, Newaygo, and Wayland

 

  • Fielding has Begun!
    • Contractors will visit each Great Lakes Energy service location to collect data, including the type of residence, pole information, and other data related to our infrastructure. This information helps us design our fiber system.
    • The expansion process takes place in three phases.
      • Phase 1 – preliminary fielding. This step started in the Hart area in mid-May and will move south. We expected fielding to wrap up by the end of the year. Once complete, we will analyze the results and make a recommendation to the GLE board of directors on the next steps. If the decision is made to move forward, the board will approve a budget, and we will proceed to the next phase.
      • Phase 2 – construction. If approved, the mainline construction will begin in mid-2021.
      • Phase 3 – installations. In-home installations would then begin in 2022.
    • Hart, Newaygo, and Wayland are now divided into smaller areas – visit jointruestream.com to view your new area name!

 


Beyond

  • Members are encouraged to register their interest at jointruestream.com to help us determine where we go next!
  • Several factors go into the decision, including demand, funding availability, and constructability of an area.