The projected dates are based on the current list of registrations from jointruestream.com which changes daily, and the current number of crews working. These dates are for drop construction progress. The drop brings the fiber line from the mainline to the side of your home. The drop generally follows the path of your electric, overhead, or underground. 

Estimated times are for construction only. Installations in the home will follow AFTER construction has been completed and the fiber line to your home has been verified as operational.

Now let’s just get to the important stuff!

To find out which area you are in, log-in to your account at jointruestream.com and view your dashboard.


Petoskey Phase 1

For everyone who HAS returned their paperwork:

  • Hayes, Resort, Petoskey West and Petoskey East
    • Underground, Underground, Underground! Crews are back at it, installing conduit and fiber from the mainline to homes (known as the drop) for those who didn’t get installed before the ground froze. We are working on burying the temporary ground lays that were done during the winter underground as well!
    • Based on current registrations and crews, most of the drops in the Petoskey Phase 1 area are projected to be completed by late spring.
    • After construction is complete and we have verified the fiber line to your home is operational, we will call to schedule the in-home installation.

For everyone who HAS NOT returned their paperwork or registered their interest:

It’s not too late, but construction and installation to your home may be delayed. Visit jointruestream.com to register your interest and so you don’t miss out.


Petoskey Phase 2

For everyone who HAS returned their paperwork:

  • West Traverse 1
    • Based on current registrations and crews, most of the drops in the West Traverse 1 area are projected to be completed by early summer.
    • After construction is complete and we have verified the fiber line to your home is operational, we will call to schedule the in-home installation.
  •  West Traverse 2
    • Based on current registrations and crews, most of the drops in the West Traverse 2 area are projected to be completed by the late spring.
    • After construction is complete and we have verified the fiber line to your home is operational, we will call to schedule the in-home installation.
  • West Traverse 3
    • Based on current registrations and crews, most of the drops in the West Traverse 3 area are projected to be completed by late spring.
    • After construction is complete and we have verified the fiber line to your home is operational, we will call to schedule the in-home installation.
  • Harbor Springs 1
    • Based on current registrations and crews, most of the drops in the Harbor Springs 1 area are projected to be completed by late summer.
    • After construction is complete and we have verified the fiber line to your home is operational, we will call to schedule the in-home installation.
  • Harbor Springs 2
    • Based on current registrations and crews, most of the drops in the Harbor Springs 2 area are projected to be late Spring.
    • After construction is complete and we have verified the fiber line to your home is operational, we will call to schedule the in-home installation.
  • Harbor Springs 3
    • Based on current registrations and crews, most of the drops in the Harbor Springs 3 area are projected to be completed by late spring.
    • After construction is complete and we have verified the fiber line to your home is operational, we will call to schedule the in-home installation.
  • Pellston 1, 2 and 3
    • Based on current registrations and crews, most of the drops in the Pellston areas are projected to be completed by mid-summer.
    • After construction is complete and we have verified the fiber line to your home is operational, we will call to schedule the in-home installation.
  • Cross Village 1 & 3 and Oden 2, 3 & 4
    • Based on current registrations and crews, most of the drops in the Cross Village and Oden areas are projected to be completed by late summer.
    • After construction is complete and we have verified the fiber line to your home is operational, we will call to schedule the in-home installation.

For everyone who HAS NOT returned their paperwork or registered their interest:

It’s not too late, but construction and installation to your home may be delayed. Visit jointruestream.com to register your interest.


Boyne Phase 1

For everyone who HAS registered their interest:

  • Boyne City 1, 2 and 3
    • Based on current registrations and crews, we expect to begin the drop installations in the Boyne City 1, 2, and 3 areas in the late summer and will continue until they are complete.
    • After construction is complete and we have verified the fiber line to your home is operational, we will call to schedule the in-home installation.
  • Advance and Deer Lake
    • Mainline construction continues
    • Be on the lookout for an email from SignNow on behalf of Truestreamfiber. The email will contain the necessary documents we need to bring our high-speed fiber internet to your home and should hit your inbox this month or early May. Return them as soon as you can!
    • Based on current registrations and crews, we expect to begin the drop installations in the Advance and Deer Lake areas in the fall and will continue until they are complete.

For everyone who HAS NOT returned their paperwork or registered their interest:

It’s not too late, but construction and installation to your home may be delayed. Visit jointruestream.com to register your interest!

 

 


Boyne Phase 2

  • Barnard, Central Lake, East Jordan, Eastport, Milton
    • Fielding will wrap up soon. This planning and engineering are the first steps to help determine the materials needed to build our fiber network!
    • Mainline construction will begin in the fall

 

 

 

 

 

 

 

 

 

 

 


Boyne Phase 3

  • Elmira & Corwith
    • Fielding is beginning. This planning and engineering steps are the first phase to help determine the materials needed to build our fiber network!
    • Pending the results of the fielding, mainline construction will likely begin in the Spring of 2021

 

 

 

 

 

 

 

 

 


Beyond

  • The board of directors has approved preliminary fieldwork in three new partial areas.
  • We are still carefully evaluating our service area to determine where we will go next.
  • Several factors go into this decision, including demand, funding availability, and constructability.