Timelines are based on the current list of registrations, which changes daily, and the current number of crews working. These dates are for construction progress. The drop brings the fiber line from the mainline to the side of the home and generally follows the path of your electric, overhead, or underground. 

Estimated times are for construction only. Installations in the home will follow AFTER construction has been completed, network equipment is installed, tested, and we have confirmed the fiber network and line to your home is operational.

If you are unsure which area your home is located in, visit the Areas status map and enter your address.

Now let’s get to the important stuff!

 


 

Boyne Phase 1

  • Boyne City, Advance, and Deer Lake
    • Mainline construction is COMPLETE!
    • Drop construction is COMPLETE!
    • Construction and in-home installations are ongoing as new registrations are received. When ready, we will call to schedule the in-home installation.
    • Be sure to give us your updated info. If you have the gray box on your home and we haven’t scheduled your installation yet, chances are we have an outdated phone number on your account.

For everyone who HAS NOT returned their paperwork or registered their interest:

Don’t miss out! Click My Account to register today! PLEASE NOTE: construction and installations in the area are ongoing, but you may experience a delay. A $149 in-home installation fee will apply.

 

 

 


Boyne Phase 2

  • East Jordan
    • Mainline construction is COMPLETE!
    • Overhead drops are COMPLETE!
    • Underground drops are ongoing.
    • After the drop construction is complete and we have verified the fiber line to your home is operational, we will call to schedule the in-home installation. Be sure your info is updated on your account!
  • Central Lake 2 and 4
    • Mainline construction is COMPLETE!
    • Drops are ongoing and expected to be complete in the late spring!
    • After the drop construction is complete and we have verified the fiber network and line to your home are operational, we will call to schedule the in-home installation. Be sure your info is updated on your account!
  • Eastport 1 and 2 
    • Mainline construction is COMPLETE!
    • Drops are ongoing and expected to be complete in the late spring!
    • Click My Account to register today! PLEASE NOTE: construction and installations in the area are ongoing, but you may experience a delay. A $149 in-home installation fee may apply.
    • After the drop construction is complete and we have verified the fiber network and line to your home are operational, we will call to schedule the in-home installation.
  • Barnard 
    • Mainline construction is COMPLETE!
    • Drops are ongoing and expected to be complete in the early summer!
    • After the drop construction is complete and we have verified the fiber network and line to your home are operational, we will call to schedule the in-home installation.
  • Eastport 3, Central Lake 3, and Milton
    • Due to extensive construction preparation work needed in the Eastport 3, Central Lake 3, and Milton areas are in a delayed status.

For everyone who HAS NOT returned their paperwork or registered their interest:

Don’t miss out! Click My Account to register today! PLEASE NOTE: construction and installations in the area are ongoing, but you may experience a delay. A $149 in-home installation fee may apply.

 


Boyne Phase 3

For everyone who registers their interest by May 1 and returns their paperwork by May 15:

  • Corwith & Elmira
    • Mainline construction has begun!
    • Drops are expected to begin in the summer and will continue until they are complete.
    • After construction is complete and we have verified the fiber network and line to your home are operational, we will call to schedule the in-home installation.

For everyone who HAS NOT returned their paperwork or registered their interest:

Don’t miss out! Click My Account to register today! PLEASE NOTE: construction and installations in the area are ongoing, but you may experience a delay. A $149 in-home installation fee may apply.

 

 


Hart Phase 1

For everyone who HAS registered interest and returned paperwork by February 1:

  • Rodgers 4 and Shelby 4
    • Mainline construction has BEGUN!
    • Drops are ongoing and expected to be complete in the summer!
    • After construction is complete, the entire area network has been lit up, and we have verified the fiber line to your home is operational, we will call to schedule the in-home installation.

For everyone who HAS NOT returned their paperwork or registered their interest:

Don’t miss out! Click My Account to register today! PLEASE NOTE: construction and installations in the area are ongoing, but you may experience a delay. A $149 in-home installation fee may apply.

Hart Phase 2

For everyone who registers their interest by May 1 and returns their paperwork by June 1:

  • Shelby 1 and 3 and Rodgers 2 and 3
    • Mainline construction has BEGUN and will continue into the summer!
    • Based on current registrations and crews, we expect to begin the drop installations in the summer and will continue until they are complete.
    • After construction is complete, the entire area network has been lit up, and we have verified the fiber line to your home is operational, we will call to schedule the in-home installation.
  •  Baseline 2 and 4 and New Era 3 and 4
    • Mainline construction has BEGUN and will continue into the summer!
    • Based on current registrations and crews, we expect to begin the drop installations in the summer and will continue until they are complete.
    • After construction is complete, the entire area network has been lit up, and we have verified the fiber line to your home is operational, we will call to schedule the in-home installation.
  • Silver Lake 2
    • Mainline construction has BEGUN and will continue into the late summer!
    • Based on current registrations and crews, we expect to begin the drop installations in the late summer and will continue until they are complete.
    • After construction is complete, the entire area network has been lit up, and we have verified the fiber line to your home is operational, we will call to schedule the in-home installation.

OFFER EXTENDED – Don’t miss out! Click My Account to register by June 15 and complete documents by July 1 to ensure construction to your home and FREE in-home installation!

 


Wayland

  • Wayland 4
    • Mainline construction will begin in late summer 2021.
    • Based on current registrations and crews, we expect to begin the drop installations in the fall and will continue until they are complete.
    • After construction is complete, the entire area network has been lit up, and we have verified the fiber line to your home is operational, we will call to schedule the in-home installation.

Don’t miss out! Click My Account to register by May 1 and complete documents by June 1 to ensure construction to your home and FREE in-home installation!

  • Middleville 1
    • Construction is delayed until 2022, pending receipt of federal forest permits.

 

 

 

 


Newaygo

  • Brohman 2 and White Cloud 3  
    • Construction is delayed until 2022, pending receipt of federal forest permits.

Petoskey 

  • Hayes, Resort, Petoskey East, Petoskey West, Oden, West Traverse, Pellston, and Cross Village
    • Mainline construction is COMPLETE!
    • Drop construction is COMPLETE!
    • Construction and in-home installations are ongoing as new registrations are received. When ready, we will call to schedule the in-home installation.

For everyone who HAS NOT returned their paperwork or registered their interest:

Don’t miss out! Click My Account to register today! PLEASE NOTE: construction and installations in the area are ongoing, but you may experience a delay. A $149 in-home installation fee will apply.

 

 

 

 

 


Waters and Kalkaska 

We’ve begun the Phase 1 fielding in our Waters service area! Phone and email notifications will be sent prior to our fielders working in your area. After the fielding process is wrapped up in Waters, we will move to the Kalkaska service area.

Waters and Kalkaska Service Area

Orange: Gathering Interest

As a reminder of the overall process:

Phase 1 is the fielding and planning phase. We will begin in Waters in March, and move into Kalkaska and finish later this year. In this phase, we collect data including the type of residence, pole information, and other data related to infrastructure. This data helps us determine the feasibility of expanding Truestream, including mapping out infrastructure needs and how to get the fiber lines to members’ homes.

Phase 2 is the construction of the fiber network. The information gathered during the Phase 1 fielding process, including a proposed budget and map of the mainline fiber route, will be presented to the board later in 2021 for approval. If approved, the construction of the fiber network would begin in 2022. This construction process can be labor intensive because it involves running the fiber line along the electrical path, which includes both underground and overhead electrical lines.

Phase 3 is when we connect homes and businesses to the Truestream network. Depending on the timeframes of Phases 1 & 2, we expect to begin connecting homes and businesses in 2023.

Free in-home installation, valued at $149, is currently available for Great Lakes Energy members who register interest.

 


Reed City and Scottville

  • Members are encouraged to pre-register their interest by clicking My Account to help us determine where we go next!
  • Several factors go into the decision, including demand, funding availability, and constructability of an area.