Timelines are based on the current list of registrations from jointruestream.com, which changes daily, and the current number of crews working. These dates are for drop construction progress. The drop brings the fiber line from the mainline to the side of the home. The drop generally follows the path of your electric, overhead, or underground. 

Estimated times are for construction only. Installations in the home will follow AFTER construction has been completed, network equipment is installed, tested, and we have confirmed the fiber network and line to your home is operational.

Now let’s get to the important stuff!

Construction is in full swing. Crews have completed over 488 drops and we have added 381 new Truestreamers so far this month!

To find out which area you are in, log-in to your account at jointruestream.com and view your dashboard.


Petoskey Service Area

For everyone who HAS returned their paperwork BEFORE May 1, 2020:

    • Mainline construction is COMPLETE!
    • Drop construction is COMPLETE!
    • In-home installations are still ongoing.

For everyone who registered and returned their paperwork AFTER May 1, 2020:

    • Design, drop construction, and in-home installations will continue, but you may experience a delay.

For everyone who HAS NOT returned their paperwork or registered their interest:

Don’t miss out! Visit www.jointruestream.com to register today! PLEASE NOTE: construction and installations in the area are ongoing, but you may experience a delay.

 

 

 

 

 


Boyne Phase 1

For everyone who HAS registered their interest and returned their paperwork BEFORE August 1, 2020:

  • Boyne City 1, 2 and 3
    • Mainline construction is COMPLETE!
    • Drop construction is COMPLETE!
    • In-home installations are ongoing. When we are scheduling in your area, we will call to schedule the in-home installation.
  • Advance and Deer Lake
    • Mainline construction is complete.
    • Based on current registrations and crews, most drops in the Advance and Deer Lake areas are projected to be COMPLETED by winter 2021.
    • After the drop construction is complete and we have verified the fiber line to your home is operational, we will call to schedule the in-home installation.

 

For everyone who HAS NOT returned their paperwork or registered their interest:

Don’t miss out! Register your interest at www.jointruestream.com by Dec. 1 and complete documents by Dec. 31 to ensure construction to your home and FREE in-home installation!


Boyne Phase 2

  • East Jordan Areas
    • Mainline construction continues.
    • Based on current registrations and crews, drops in the East Jordan areas are projected to BEGIN in early 2021.
    • After construction is complete and we have verified the fiber network and line to your home are operations, we will call to schedule the in-home installation.
  • Central Lake and Eastport 1 and 2 Areas
    • Mainline construction has begun in Central Lake 2, 3, and 4 and Eastport 1, 2, and 3 areas.
    • Based on current registrations and crews, drops in the Central Lake and Eastport areas are projected to BEGIN in the spring of 2021.
    • After the drop construction is complete and we have verified the fiber line to your home is operational, we will call to schedule the in-home installation.
  • Barnard Areas
    • Mainline construction has begun.
    • Based on current registrations and crews, drops in the Barnard and Milton areas are projected to BEGIN in the summer of 2021.
    • After the drop construction is complete and we have verified the fiber line to your home is operational, we will call to schedule the in-home installation.
  • Eastport 3 and Milton Areas
    • Due to extensive construction preparation work needed in the Eastport 3 and Milton areas, a majority of the mainline construction will begin in 2021.

For everyone who HAS NOT returned their paperwork or registered their interest:

Don’t miss out! Register your interest at www.jointruestream.com by Jan. 15 and complete documents by Feb. 15 to ensure construction to your home and FREE in-home installation!

 


Boyne Phase 3

Boyne Phase 3 Map

  • Elmira & Corwith
    • Mainline construction will begin in the spring of 2021
    • Based on current registrations and crews, we expect to begin the drop installations in the Boyne phase 3 areas in the summer of 2021 and will continue until they are complete.
    • After construction is complete and we have verified the fiber line to your home is operational, we will call to schedule the in-home installation.

For everyone who HAS NOT returned their paperwork or registered their interest:

Don’t miss out! Register your interest at www.jointruestream.com by Apr. 1 and complete documents by May 1 to ensure construction to your home and FREE in-home installation!

 

 


Hart

  • Rodgers 4 and Shelby 4
    • Mainline construction and drops will begin early 2021.
    • After construction is complete, the entire area network has been lit up, and we have verified the fiber line to your home is operational, we will call to schedule the in-home installation.

Don’t miss out! Register your interest at www.jointruestream.com by Dec. 1 and complete documents by Dec. 31 to ensure construction to your home and FREE in-home installation!

 

 

 

 

 


Newaygo

  • Brohman 2 and White Cloud 3
    • Mainline construction and drops will begin in late winter..
    • After construction is complete, the entire area network has been lit up, and we have verified the fiber line to your home is operational, we will call to schedule the in-home installation.

Don’t miss out! Register your interest at www.jointruestream.com by Jan. 15 and complete documents by Feb. 15 to ensure construction to your home and FREE in-home installation!

 

 

 

 

 


Wayland

  • Middleville 1 and Wayland 4
    • Mainline construction and drops will begin in early summer 2021.
    • After construction is complete, the entire area network has been lit up, and we have verified the fiber line to your home is operational, we will call to schedule the in-home installation.

Don’t miss out! Register your interest at www.jointruestream.com by Apr. 1 and complete documents by May 1 to ensure construction to your home and FREE in-home installation!

 

 

 

 

 

 


Beyond

  • Members are encouraged to register their interest at jointruestream.com to help us determine where we go next!
  • Several factors go into the decision, including demand, funding availability, and constructability of an area.